Framework for Integrating Software Project Tasks and Change Requests

by Amira M. Gaber, Sherief Mazen, Ehab E. Hassanei
International Journal of Computer Applications
Foundation of Computer Science (FCS), NY, USA
Volume 125 - Number 12
Year of Publication: 2015
Authors: Amira M. Gaber, Sherief Mazen, Ehab E. Hassanei
10.5120/ijca2015906150

Amira M. Gaber, Sherief Mazen, Ehab E. Hassanei . Framework for Integrating Software Project Tasks and Change Requests. International Journal of Computer Applications. 125, 12 ( September 2015), 24-30. DOI=10.5120/ijca2015906150

@article{ 10.5120/ijca2015906150,
author = { Amira M. Gaber, Sherief Mazen, Ehab E. Hassanei },
title = { Framework for Integrating Software Project Tasks and Change Requests },
journal = { International Journal of Computer Applications },
issue_date = { September 2015 },
volume = { 125 },
number = { 12 },
month = { September },
year = { 2015 },
issn = { 0975-8887 },
pages = { 24-30 },
numpages = {9},
url = { https://ijcaonline.org/archives/volume125/number12/22485-2015906150/ },
doi = { 10.5120/ijca2015906150 },
publisher = {Foundation of Computer Science (FCS), NY, USA},
address = {New York, USA}
}
%0 Journal Article
%1 2024-02-06T23:15:52.306483+05:30
%A Amira M. Gaber
%A Sherief Mazen
%A Ehab E. Hassanei
%T Framework for Integrating Software Project Tasks and Change Requests
%J International Journal of Computer Applications
%@ 0975-8887
%V 125
%N 12
%P 24-30
%D 2015
%I Foundation of Computer Science (FCS), NY, USA
Abstract

Most of the software projects may deviate from their original plans during the Software Life Cycle in the organization. This deviation typically results from the changes that happed and the project manager depends on his experience to estimate the effects of the change. This may affect the duration and budget of the project. It is important that the software project should not deviate or crash according to the estimated deadline. Thus any change should be estimated and discussed before implementation. In this paper will introduce a framework that integrates the Software Project Management (SPM) with Software Change Management (SCM) to achieve the following objectives: Firstly, optimizing the Change Management Process in a project and track the whole Change Requests. Secondly, monitoring if the software project finished early by revising the project plan w.r.t the actual schedule to shrink the project deadline. And execute the consequences processes according to finish early. Thirdly, the actual results with performance will be tracked against the project plan and any variances should be analyzed. In addition, facilitating distribution of tasks (Change Requests) and availability of information. Finally, providing more control over a project when the technical issues can be raised and turned to managerial issues to take corrective actions if: the project takes more time, the project takes more cost or both of them

References
  1. A. R. M. Nordin , S. Suhailan. 2009. Managing Software Change Request Process: Temporal Data Approach. International Journal of Computer Science and Security, (IJCSS) Volume (3) : Issue (3).
  2. www.mosaicprojects.com.au
  3. Olsen, N. 1993. The software rush hour. In IEEE Software Magazine. IEEE. Pp. 29 – 37. (September).
  4. S. M. Ghosh , H. R. Sharma, V. Mohabay. 2011. Analysis and Modeling of Change Management Process Model.
  5. Dijkstra, E.W. 1959. A note on two problems in connection with graphs, Numerische Mathematik, 1, 269-271.
  6. Kelley, J.E. and Walker, M.R. (1959), Critical path planning and scheduling, Eastern Joint Computer Conference, 16, 160-172.
  7. R. Morovatdar, A. Aghaie, E. Roghanian, A. Asl Haddad. 2013. An Algorithm to Obtain Possibly Critical Paths in Imprecise Project Networks", Iranian Journal of Operations Research,Vol. 4, No. 1, pp. 39-54
  8. GET EGYPT, Inc. (2009) www.getgroup.com
  9. Mantrac Unatrac Group, Inc. (2013). www.mantracgroup.com.
Index Terms

Computer Science
Information Sciences

Keywords

Software Project Management (SPM) Software Change Management Software Configuration Change Board (SCCB) Change Requests (CRs) Work Breakdown Structure (WBS) Change Request Breakdown Structure (CRBS).